01 / Direct answerDivide the required load energy by the confirmed usable battery fraction and system efficiency.
The search question is: how many kWh of LiFePO4 battery does a solar system need? First calculate the energy the protected loads will use. Then convert that AC-load energy into nominal battery energy with this planning formula: nominal battery kWh = load kWh ÷ (usable battery fraction × inverter efficiency).
For example, a 1 kW average essential load running for four hours uses 4 kWh. If a preliminary design assumes an 80% usable fraction and 90% inverter efficiency, the nominal target is 4 ÷ (0.80 × 0.90) = 5.56 kWh. Those percentages are visible planning assumptions, not SAVYEN product guarantees; replace them with the limits and efficiency data confirmed for the exact battery and inverter.
Short answer
Calculate load kWh, divide by confirmed usable fraction and efficiency, add a justified reserve, then select the next practical battery configuration that also meets current and compatibility limits.
Do not size from inverter kW alone
Inverter kW describes power. Battery kWh describes stored energy. A 5 kW inverter does not automatically require or provide five hours from a 5 kWh battery.
02 / Load energyBuild an essential-load schedule before choosing a battery model.
For each protected appliance, multiply running power in kW by operating time in hours. Add the results. Use a measured load profile where possible and a realistic duty cycle for refrigerators, pumps, air conditioners and other equipment that cycles rather than running continuously.
Separate normal running energy from starting surge. Surge changes the instantaneous power and current requirement, while the operating schedule determines energy. Both must be checked, but they are not interchangeable.
Worked load schedule
Lights: 0.20 kW × 5 h = 1.00 kWh. Refrigerator average: 0.15 kW × 10 h = 1.50 kWh. Electronics: 0.10 kW × 5 h = 0.50 kWh. Total load energy = 3.00 kWh.
Average versus peak
An average-energy calculation can hide a short high-power event. Record motor starts and simultaneous loads for inverter and battery-current checks.
Backup window
Define whether the target is a four-hour outage, overnight autonomy or a full off-grid day. The same equipment needs different battery energy for each window.
03 / Nominal capacityConvert the energy target into kWh and Ah without treating nameplate energy as delivered AC energy.
Battery energy is calculated from nominal voltage and amp-hours: nominal kWh = V × Ah ÷ 1,000. SAVYEN's published 51.2 V models therefore include 5.12 kWh at 100 Ah, 10.24 kWh at 200 Ah and 16.076 kWh at 314 Ah.
These are rated-energy values. The energy delivered to AC loads can be lower because the permitted operating window, inverter conversion, cabling, temperature, ageing, standby consumption and protection settings affect the result. Confirm the usable basis for the exact quotation rather than applying one percentage to every model.
3 kWh load example
Using illustrative assumptions of 80% usable fraction and 90% inverter efficiency: 3 ÷ (0.80 × 0.90) = 4.17 kWh nominal before any additional reserve.
8 kWh load example
Using the same illustrative assumptions: 8 ÷ (0.80 × 0.90) = 11.11 kWh nominal. This exceeds one 10.24 kWh nameplate battery, so a larger or parallel configuration would need model-level confirmation.
Ah conversion
After the voltage platform is fixed, Ah = nominal Wh ÷ nominal V. Do not compare Ah across 12.8 V, 25.6 V and 51.2 V batteries without converting to energy.
04 / Power and currentVerify that the selected battery can supply the load as well as store enough energy.
A first-pass DC-current estimate is inverter output power ÷ (battery voltage × inverter efficiency). At 5 kW, 51.2 V and an illustrative 90% efficiency, the estimate is 5,000 ÷ (51.2 × 0.90) = approximately 108.5 A. This is a planning estimate, not an equipment rating.
Compare the result with the exact battery's continuous and peak limits, the inverter's DC demand, cable and protective-device ratings, and any derating conditions. The published 51.2 V 100 Ah product lists a 100 A maximum discharge current, while the 51.2 V 200 Ah product lists 200 A maximum continuous discharge at its stated temperature condition. Those facts do not by themselves approve either model for a specific inverter or surge profile.
Continuous load
Check the expected worst-case sustained DC current, not only the average energy use.
Starting surge
Motors, compressors and pumps may demand a short surge. Confirm the inverter and battery limits and duration on the same basis.
Parallel systems
Use only model-approved parallel quantities, matched units, equal-current cabling, suitable protection and the manufacturer's commissioning procedure.
05 / Solar rechargeCheck whether the PV array can replace the energy used during the backup period.
Battery sizing and solar-array sizing are related but separate. The battery must cover the required load energy and power. The PV array must serve daytime loads and provide enough additional energy to recharge the battery under the site's solar resource and system losses.
A larger battery does not solve an undersized PV array. For an off-grid or frequently cycled system, review seasonal solar hours, weather variability, recharge time, generator or grid support and the charge-current limits of the battery and inverter.
Energy balance
Estimate daily load kWh, available PV energy and conversion losses across the relevant season rather than relying on panel wattage alone.
Recharge deadline
Define whether the battery must recover in one solar day, over several days or with grid or generator assistance.
06 / Final selectionConfirm the complete battery-and-inverter system before ordering.
Send the load schedule, maximum simultaneous power, surge loads, backup target, inverter brand and exact model, destination country, site conditions, quantity and expansion plan. Ask for written confirmation of the selected battery model, usable-energy basis, current limits, communication protocol, operating settings, included accessories and parallel architecture.
Voltage class alone does not prove compatibility. CAN and RS485 name communication methods, but the protocol, firmware, cable pinout and inverter settings must match the exact battery-and-inverter pair.
Electrical inputs
Load kW, load kWh, surge, backup hours, inverter model, voltage platform and recharge source.
Site inputs
Temperature, indoor or outdoor location, altitude, dust, humidity, cable distance and available installation space.
Commercial inputs
Quantity, destination, delivery term, required documentation, OEM needs and future expansion plan.
SOURCESProduct data and related evidence.
Use these public sources to verify the model facts used in this guide. Final order specifications still require written confirmation.